On Thursday, Oct. 30, the contractor began paving Taumarson Road, Highland Road, and a portion of the Myra Road extension. This week, crews continued installing signage, advancing stormwater system improvements, and performing concrete work throughout the project area, including significant curb and gutter work at the SR-125 roundabout.
Next week, crews are scheduled to complete additional paving and begin installing streetlights.
Taumarson Road Closure:
Taumarson Road is anticipated to reopen in late November 2025. The City thanks residents for their patience throughout the Myra Road South Extension project.
•Learn more: https://www.gowallawalla.us/myra-south